Ch10. Project Management Comprehensive Review — PMP Exam Prep and Practical Checklists
Series Summary — All Ten Chapters
| Chapter | Topic | Core Concepts |
|---|---|---|
| Ch1 | Management Framework | PMBOK, process groups |
| Ch2 | Scope & Schedule Management | WBS, critical path |
| Ch3 | Resource & Cost Management | RAM, EVM |
| Ch4 | Quality & Risk Management | PDCA, risk matrix |
| Ch5 | Stakeholder & Communications | Influence mapping, RACI |
| Ch6 | Project Integration Management | Charter, change control |
| Ch7 | Agile vs. Waterfall | Scrum, Kanban |
| Ch8 | Procurement & Contracts | FP, T&M, CR |
| Ch9 | Project Closure | Lessons learned, final report |
| Ch10 | Comprehensive Review | PMP preparation |
The 10 PMBOK Knowledge Areas
1. Integration Management
2. Scope Management
3. Schedule Management
4. Cost Management
5. Quality Management
6. Resource Management
7. Communications Management
8. Risk Management
9. Procurement Management
10. Stakeholder Management
The 5 Process Groups
Initiating:
→ Develop project charter / Identify stakeholders
Planning:
→ Develop the overall management plan / Establish baselines
Executing:
→ Direct and manage project work / Manage team / Quality assurance
Monitoring & Controlling:
→ Measure project performance / Integrated change control
Closing:
→ Accept deliverables / Document lessons learned / Close contracts
Key PMP Formulas
EVM (Earned Value Management)
PV (Planned Value): Budgeted value of work scheduled to be done by this point
EV (Earned Value): Budgeted value of work actually completed
AC (Actual Cost): Actual cost incurred to date
Variances:
SV (Schedule Variance) = EV − PV (positive = ahead of schedule)
CV (Cost Variance) = EV − AC (positive = under budget)
Performance Indices:
SPI (Schedule Performance Index) = EV ÷ PV (1.0 = on track)
CPI (Cost Performance Index) = EV ÷ AC (1.0 = on track)
Forecasts:
BAC (Budget at Completion)
EAC (Estimate at Completion) = BAC ÷ CPI
ETC (Estimate to Complete) = EAC − AC
Communication Channels Formula
Number of channels = n(n − 1) ÷ 2
(n = number of team members)
Example: 10-person team = 10 × 9 ÷ 2 = 45 channels
→ As team size grows, communication complexity grows exponentially
Practical PM Checklist
Project Initiation
☐ Project charter drafted and signed by the sponsor
☐ Key stakeholders identified and analyzed (power/interest grid)
☐ Kickoff meeting held
☐ Initial risk list drafted
Planning Phase
☐ WBS created (with team participation)
☐ Network diagram built → critical path identified
☐ Resource histogram reviewed → peaks identified → leveled
☐ Cost baseline and contingency reserves set
☐ Risk register complete (probability × impact matrix)
☐ Communications plan defined (who, when, what format)
Executing and Controlling Phase
☐ Weekly status reports (plan vs. actuals)
☐ EVM metrics tracked (SPI, CPI ≥ 0.8)
☐ Risk register reviewed regularly (monthly)
☐ Change requests → CCB review → baseline updated
☐ Quality reviews conducted and defects tracked
Closing Phase
☐ Final deliverables accepted (signed acceptance document)
☐ Lessons learned session held and documented
☐ All procurement contracts formally closed
☐ Team members' contributions recognized and transitions communicated
☐ Project records archived
Core PM Competencies
Technical Competence:
→ PMBOK methodology, EVM, risk analysis
Leadership Competence:
→ Motivation, conflict resolution, communication
Strategic Competence:
→ Understanding the business context
→ Aligning project outcomes with organizational strategy
→ PMI's emphasis: balancing all three is the hallmark of a successful PM
A good PM makes a plan. A great PM prepares for when the plan is wrong.
O
OIYO Editorial
Content Editor지식 인큐베이터이자 전문 콘텐츠 크리에이터. 경영, 경제, 법률 및 실생활에 유용한 실무/자격증 중심의 깊이 있는 정보를 연구하고 공유합니다.