Business Chapter 10 4 min read

Ch10. Project Management Comprehensive Review — PMP Exam Prep and Practical Checklists

O
OIYO Editorial Contributor
10/10

Series Summary — All Ten Chapters

ChapterTopicCore Concepts
Ch1Management FrameworkPMBOK, process groups
Ch2Scope & Schedule ManagementWBS, critical path
Ch3Resource & Cost ManagementRAM, EVM
Ch4Quality & Risk ManagementPDCA, risk matrix
Ch5Stakeholder & CommunicationsInfluence mapping, RACI
Ch6Project Integration ManagementCharter, change control
Ch7Agile vs. WaterfallScrum, Kanban
Ch8Procurement & ContractsFP, T&M, CR
Ch9Project ClosureLessons learned, final report
Ch10Comprehensive ReviewPMP preparation

The 10 PMBOK Knowledge Areas

1. Integration Management
2. Scope Management
3. Schedule Management
4. Cost Management
5. Quality Management
6. Resource Management
7. Communications Management
8. Risk Management
9. Procurement Management
10. Stakeholder Management

The 5 Process Groups

Initiating:
→ Develop project charter / Identify stakeholders

Planning:
→ Develop the overall management plan / Establish baselines

Executing:
→ Direct and manage project work / Manage team / Quality assurance

Monitoring & Controlling:
→ Measure project performance / Integrated change control

Closing:
→ Accept deliverables / Document lessons learned / Close contracts

Key PMP Formulas

EVM (Earned Value Management)

PV (Planned Value):   Budgeted value of work scheduled to be done by this point
EV (Earned Value):    Budgeted value of work actually completed
AC (Actual Cost):     Actual cost incurred to date

Variances:
SV (Schedule Variance) = EV − PV   (positive = ahead of schedule)
CV (Cost Variance)     = EV − AC   (positive = under budget)

Performance Indices:
SPI (Schedule Performance Index) = EV ÷ PV  (1.0 = on track)
CPI (Cost Performance Index)     = EV ÷ AC  (1.0 = on track)

Forecasts:
BAC (Budget at Completion)
EAC (Estimate at Completion)  = BAC ÷ CPI
ETC (Estimate to Complete)    = EAC − AC

Communication Channels Formula

Number of channels = n(n − 1) ÷ 2
(n = number of team members)

Example: 10-person team = 10 × 9 ÷ 2 = 45 channels
→ As team size grows, communication complexity grows exponentially

Practical PM Checklist

Project Initiation

☐ Project charter drafted and signed by the sponsor
☐ Key stakeholders identified and analyzed (power/interest grid)
☐ Kickoff meeting held
☐ Initial risk list drafted

Planning Phase

☐ WBS created (with team participation)
☐ Network diagram built → critical path identified
☐ Resource histogram reviewed → peaks identified → leveled
☐ Cost baseline and contingency reserves set
☐ Risk register complete (probability × impact matrix)
☐ Communications plan defined (who, when, what format)

Executing and Controlling Phase

☐ Weekly status reports (plan vs. actuals)
☐ EVM metrics tracked (SPI, CPI ≥ 0.8)
☐ Risk register reviewed regularly (monthly)
☐ Change requests → CCB review → baseline updated
☐ Quality reviews conducted and defects tracked

Closing Phase

☐ Final deliverables accepted (signed acceptance document)
☐ Lessons learned session held and documented
☐ All procurement contracts formally closed
☐ Team members' contributions recognized and transitions communicated
☐ Project records archived

Core PM Competencies

Technical Competence:
→ PMBOK methodology, EVM, risk analysis

Leadership Competence:
→ Motivation, conflict resolution, communication

Strategic Competence:
→ Understanding the business context
→ Aligning project outcomes with organizational strategy

→ PMI's emphasis: balancing all three is the hallmark of a successful PM

A good PM makes a plan. A great PM prepares for when the plan is wrong.

O

OIYO Editorial

Content Editor

지식 인큐베이터이자 전문 콘텐츠 크리에이터. 경영, 경제, 법률 및 실생활에 유용한 실무/자격증 중심의 깊이 있는 정보를 연구하고 공유합니다.