Project Management Comprehensive Review — PMP Exam Prep and Practical Checklists
Series Summary — All Ten Chapters
| Chapter | Topic | Core Concepts |
|---|---|---|
| Ch1 | Management Framework | PMBOK, process groups |
| Ch2 | Scope & Schedule Management | WBS, critical path |
| Ch3 | Resource & Cost Management | RAM, EVM |
| Ch4 | Quality & Risk Management | PDCA, risk matrix |
| Ch5 | Stakeholder & Communications | Influence mapping, RACI |
| Ch6 | Project Integration Management | Charter, change control |
| Ch7 | Agile vs. Waterfall | Scrum, Kanban |
| Ch8 | Procurement & Contracts | FP, T&M, CR |
| Ch9 | Project Closure | Lessons learned, final report |
| Ch10 | Comprehensive Review | PMP preparation |
The 10 PMBOK Knowledge Areas
- Integration Management
- Scope Management
- Schedule Management
- Cost Management
- Quality Management
- Resource Management
- Communications Management
- Risk Management
- Procurement Management
- Stakeholder Management
The 5 Process Groups
Initiating:
- Develop project charter / Identify stakeholders
Planning:
- Develop the overall management plan / Establish baselines
Executing:
- Direct and manage project work / Manage team / Quality assurance
Monitoring & Controlling:
- Measure project performance / Integrated change control
Closing:
- Accept deliverables / Document lessons learned / Close contracts
Key PMP Formulas
EVM (Earned Value Management)
PV (Planned Value): Budgeted value of work scheduled to be done by this point
EV (Earned Value): Budgeted value of work actually completed
AC (Actual Cost): Actual cost incurred to date
Variances:
SV (Schedule Variance) = EV − PV (positive = ahead of schedule)
CV (Cost Variance) = EV − AC (positive = under budget)
Performance Indices:
SPI (Schedule Performance Index) = EV ÷ PV (1.0 = on track)
CPI (Cost Performance Index) = EV ÷ AC (1.0 = on track)
Forecasts:
BAC (Budget at Completion)
EAC (Estimate at Completion) = BAC ÷ CPI
ETC (Estimate to Complete) = EAC − AC
Communication Channels Formula
Practical PM Checklist
Project Initiation
☐ Project charter drafted and signed by the sponsor
☐ Key stakeholders identified and analyzed (power/interest grid)
☐ Kickoff meeting held
☐ Initial risk list drafted
Planning Phase
☐ WBS created (with team participation)
☐ Network diagram built → critical path identified
☐ Resource histogram reviewed → peaks identified → leveled
☐ Cost baseline and contingency reserves set
☐ Risk register complete (probability × impact matrix)
☐ Communications plan defined (who, when, what format)
Executing and Controlling Phase
☐ Weekly status reports (plan vs. actuals)
☐ EVM metrics tracked (SPI, CPI ≥ 0.8)
☐ Risk register reviewed regularly (monthly)
☐ Change requests → CCB review → baseline updated
☐ Quality reviews conducted and defects tracked
Closing Phase
☐ Final deliverables accepted (signed acceptance document)
☐ Lessons learned session held and documented
☐ All procurement contracts formally closed
☐ Team members’ contributions recognized and transitions communicated
☐ Project records archived
Core PM Competencies
Technical Competence:
- PMBOK methodology, EVM, risk analysis
Leadership Competence:
- Motivation, conflict resolution, communication
Strategic Competence:
-
Understanding the business context
-
Aligning project outcomes with organizational strategy
-
PMI’s emphasis: balancing all three is the hallmark of a successful PM
A good PM makes a plan. A great PM prepares for when the plan is wrong.
OIYO Editorial
Editorial DeskThe OIYO editorial desk researches money, law, lifestyle, and self-understanding topics against primary sources and public statistics. Every piece carries source notes and is reviewed on a regular cycle for accuracy and usefulness.