Ch3. Scope, Schedule, and Cost Management — The Triple Constraint
The Triple Constraint
All projects operate within three interrelated constraints:
Scope
△
/ \
/ \
/ \
Schedule ──── Cost
Changing one affects the others. The PM’s job is to manage this balance.
Scope Management
WBS (Work Breakdown Structure)
Hierarchical decomposition of the total project work into manageable components.
Project
├── 1. Planning
│ ├── 1.1 Requirements gathering
│ └── 1.2 Scope definition
├── 2. Development
│ ├── 2.1 Backend
│ └── 2.2 Frontend
└── 3. Testing
└── 3.1 QA
Work packages: The lowest level WBS elements — small enough to estimate schedule and cost.
Scope Creep
Gradual, unauthorized expansion of scope without formal approval. A leading cause of project failure.
Prevention: Formal change control process, documented scope baseline, clear stakeholder communication.
Exam answer pattern: When a stakeholder requests a new feature informally, the correct PM action is always to direct them through the formal Change Control Process — not to immediately accept or reject the request.
Schedule Management: Critical Path Method (CPM)
Calculates the minimum project duration and identifies which activities have schedule flexibility.
Critical path: The longest sequence of activities = minimum project duration.
Activity A (3 days) → Activity C (2 days)
→ End (CPM = 8 days)
Activity B (5 days) → Activity D (3 days)
Critical path: B → D (8 days) Path A → C = 5 days → Float = 3 days (can be delayed up to 3 days without delaying the project)
Float (slack): How long an activity can be delayed without impacting the end date.
- Activities on the critical path have Float = 0
Cost Management: Earned Value Management (EVM)
Integrates scope, schedule, and cost data to provide an objective view of project performance.
Core Metrics
| Metric | Formula | Meaning |
|---|---|---|
| PV | Planned Value | Budgeted value of work planned to be done by now |
| EV | Earned Value | Budgeted value of work actually completed |
| AC | Actual Cost | Actual amount spent so far |
Variances and Indices
| Metric | Formula | Interpretation |
|---|---|---|
| CV | EV – AC | Positive=under budget, Negative=over budget |
| SV | EV – PV | Positive=ahead of schedule, Negative=behind |
| CPI | EV / AC | >1=efficient, <1=over-spending |
| SPI | EV / PV | >1=ahead, <1=behind |
Example:
Mid-project checkpoint:
PV = $500K (planned to complete $500K of work by now)
EV = $400K (only $400K of work actually completed)
AC = $480K (spent $480K)
CV = 400 - 480 = -80K (over budget)
SV = 400 - 500 = -100K (behind schedule)
CPI = 400/480 = 0.83 (generating $0.83 of value per dollar spent)
SPI = 400/500 = 0.80 (80% of planned progress achieved)
Key Concept Cards
WBS ★★★★★ : Hierarchical scope decomposition. Foundation for schedule and cost estimation. No work should be missing.
Critical Path ★★★★★ : Activities with Float=0 define the project’s minimum duration. Any delay here delays the project.
CPI and SPI ★★★★★ : Above 1.0 = good, below 1.0 = problem. CPI=cost efficiency, SPI=schedule efficiency. Core EVM metrics.
Practice Quiz
Q1. A project has CPI = 0.8 and SPI = 1.2. What does this mean?
The project is ahead of schedule (SPI > 1) but over budget (CPI < 1). Work is being completed faster than planned, but more money is being spent than budgeted to accomplish it. The PM must investigate cost overruns and update the cost forecast (EAC).
Q2. What is the most effective way to prevent scope creep?
Establish and enforce a formal Change Control Process. All scope changes must go through this process — no informal additions. Maintain a clear, documented scope baseline; educate stakeholders on the process; and conduct regular scope reviews. Documentation is defense against unauthorized changes.
OIYO Editorial
Editorial DeskThe OIYO editorial desk researches money, law, lifestyle, and self-understanding topics against primary sources and public statistics. Every piece carries source notes and is reviewed on a regular cycle for accuracy and usefulness.